Mitigation Monitoring and Reporting Matrix (continued)

 

 

Significant Impact Being Mitigated

 

Mitigation Measure

 

Responsibility for Implementation

 

Enforcement Responsibility

Monitoring Responsibility/ Frequency

 

Actions Indicating Compliance

Biological Resources (cont.)

 

 

 

 

during the flowering period when each species is most readily identifiable.

  1. Demonstrate that three special-status plant surveys were conducted at two-week intervals during the flowering period (April to June.
  2. Identify whether a special-status plant species has colonized the site in the interim between the determination of baseline conditions for the EIR, and project initiation; and
  3. If any special status plant populations are identified during surveys, provide accurate mapping of the special status plant populations and achieve the requirements of Mitigation Measure 4.C- 1b by determining whether trails could be sited to avoid special- status plants and Viola pedunculata.
  4. If trails could be designed to avoid status plants and Viola pedunculata, provide site-specific direction for final trail routing and design, including a minimum 25 foot buffer zone adjacent to the trail

 