Significant Impact Being Mitigated |
Mitigation Measure |
Responsibility for Implementation |
Enforcement Responsibility |
Monitoring Responsibility/ Frequency |
Actions Indicating Compliance |
Hazards and Hazardous Materials (cont.) |
|||||
|
|
|
|
The City Building Official shall review also all plans for construction of structures within 1,000 feet of the landfill footprint ensure the provision of automatic combustible gas sensors in sub-floor areas and in the first floor of occupied interior spaces of buildings. Gas monitoring for trace gases shall be conducted in accordance with the requirements of Title 27 as specified in Mitigation Measure 4.G-2h. |
|
Potential lead contamination on Icehouse Hill from the former shooting range. DSP, DSP-V, CPP, & CPP-V scenarios |
4.G-2i: Prior to any construction of trails on the southerly slope of Icehouse Hill, best management practices for lead removal consistent with United States Environmental Protection Agency Circular EPA- 902-B-01-001, Best Management Practices for Lead at Outdoor Shooting Ranges, Revised June 2005, shall be implemented. |
Contractor for trail construction |
City of Brisbane Community Development Director |
Prior to authorizing construction of trails on the southerly slope of Icehouse Hill, the City Building Official shall review construction contracts for the trails to ensure that best management practices for lead removal as required by Mitigation Measure 4.G-2i will be completed prior to trail construction. |
Lead removal consistent with United States Environmental Protection Agency Circular EPA-902- B-01-001, Best Management Practices for Lead at Outdoor Shooting Ranges, Revised June 2005 prior to construction of trails on the southerly slope of Icehouse Hill. |
Potential contamination within the Bayshore Industrial Park. DSP, DSP-V, CPP, & CPP-V scenarios |
4.G-2j: Prior to approval of any demolition plan within the Bayshore Industrial Park, any building(s) proposed for demolition shall be tested for asbestos and lead- based paint. Should asbestos or lead-based paint be identified, the affected building(s) shall be remediated to the satisfaction of the RWQCB pursuant to the most current regulatory standards in effect at the time of remediation. Prior to site development within the Bayshore Industrial Park, soils shall be tested for likely constituents of concern based on the site’s use pursuant to the requirements of the RWQCB. Human |
Site-specific developer(s) |
City of Brisbane Building Official |
The City Building Official shall not issue a permit for demolition of any buildings within the Bayshore Industrial Park until testing for asbestos and lead- based paint is completed to the Building Official’s satisfaction. Should asbestos or lead- based paint be identified, |
Approval of demolition permits for buildings within the Bayshore Industrial Park in compliance with Mitigation Measure 4.G-2j. |