Mitigation Monitoring and Reporting Matrix (continued)

 

 

Significant Impact Being Mitigated

 

Mitigation Measure

 

Responsibility for Implementation

 

Enforcement Responsibility

Monitoring Responsibility/ Frequency

 

Actions Indicating Compliance

Air Quality (cont.)

Generate cumulatively considerable construction emissions of criteria pollutants

DSP, DSP-V, CPP, &

CPP-V scenarios

4.B-2b: All construction contract specifications shall include a requirement that off-road construction equipment used for site improvements shall be equipped with Tier 3 (Tier 2 if greater than 750 hp) diesel engines or better. All diesel generators used for project construction must meet Tier 4 emissions standards. If new emissions standards are adopted by

U.S. EPA during project construction, construction contract specifications shall incorporate whichever standard is more stringent.

Construction contractors for site-specific development

The City Building Official shall not approve any building permit applications without evidence that the required language is included in construction contracts and specifications.

The City Engineer shall not approve any grading permit or infrastructure improvements plan without evidence that the required language is included in construction contracts and specifications.

The City Building Official shall be responsible for monitoring compliance on a minimum monthly basis during building construction.

The City Engineer shall be responsible for monitoring compliance on a minimum monthly basis during grading and infrastructure construction.

Approval of building, grading, and construction permits in compliance with Mitigation Measure 4.B-2a.

Considerable net increase of criteria pollutants during operations

DSP, DSP-V, CPP, &

CPP-V scenarios

4.B-4: The following measures identified in the 2012 BAAQMD CEQA Guidelines shall be implemented for site-specific development projects within the Project Site and shall be included, as applicable, into commercial leases, as well as Covenants, Codes, and Restrictions (CC&Rs) within the Project Site:

  1. Provide free transit passes (e.g., Clipper Card for use on Caltrain, San Francisco Municipal Railway [Muni], and SAMTrans) to employees (for employers of 100 or more employees);
  2. Provide and maintain secure bike parking for commercial and industrial uses (at least one space per 20 vehicle spaces) as a condition of occupancy permit/tenancy contract;
  3. Provide and maintain showers and changing facilities for employees in buildings having a gross leasable area of 25,000 square feet or more;
  4. Provide information on transportation alternatives to employees as a condition of occupancy permit/tenancy contract;
  5. Establish a dedicated employee transportation coordinator for each site-specific development as a condition of occupancy permit/tenancy contract;

Businesses with 100 or more employees shall provide free transit passes (e.g., Clipper Card for use on Caltrain, San Francisco Municipal Railway [Muni], and SAMTrans) to employees as part of approved TDM programs.

Site developers shall design parking areas with a minimum of 20 spaces for commercial and industrial uses to:

  • Provide a minimum of 1 secure bicycle parking space for each 20 vehicle parking spaces. Building owners responsible for maintaining areas shall also be responsible for maintaining secure bicycle parking spaces.

City of Brisbane Community Development Director

The Community Development Director shall ensure that provisions i through vi of Mitigation Measure 4.B-4 are included in the Transportation Demand Management Program required by Mitigation Measure 4.N-13.

The Community Development Director shall prepare a condition of approval for site-specific development that provisions vii through xiii of Mitigation Measure 4.B-4 shall be included into all commercial leases and CC&Rs.

Approval of TDM program(s) meeting City and C/CAG requirements prior to issuance of occupancy permits.

Approval of site-specific developments with conditions of approval requiring implementation of provisions vii through xiii of Mitigation Measure 4.B-4 to be included into all commercial leases and CC&Rs.