Significant Impact Being Mitigated |
Mitigation Measure |
Responsibility for Implementation |
Enforcement Responsibility |
Monitoring Responsibility/ Frequency |
Actions Indicating Compliance |
Noise and Vibration (cont.) |
|||||
|
Site design measures, including use of building orientation to minimize window exposure toward noise sources, avoid placing balcony areas in high noise areas, and use of buildings as noise barriers;
|
|
|
|
|
Exposure of onsite residents to vibration from rail operations. DSP and DSP-V scenarios. |
Measure 4.J-2a: All development in the Baylands shall be designed to avoid vibration from Caltrain operations in excess of 72 VdB for residences. Prior to issuance of any building permit for structures intended for human occupancy within 200 feet of the mainline track, a detailed vibration design study shall be completed by a qualified acoustical engineer to confirm the ground vibration levels and frequency content along the Caltrain tracks and to determine appropriate design to limit interior vibration levels to 72 VdB for residences. Implementation of the recommended measures of the acoustical study into project design elements shall be verified by the Brisbane Building Department as part of the plan-check process. Specific measures to achieve the performance standards set forth above shall include all or any combination of the following methods:
|
Applicant(s) for development of residential structures intended for human occupancy within 200 feet of the Caltrain mainline track shall provide a vibration design study prepared by a qualified acoustical professional verifying that the performance standards set forth in Mitigation Measure 4.J-2a will be achieved. |
City of Brisbane Building Official |
Prior to issuing any building permit(s) for residential structures intended for human occupancy within 200 feet of the Caltrain mainline track, the City Building Official shall review the vibration design study prepared for the applicant by a qualified acoustical professional to ensure that the performance standards set forth in Mitigation Measure 4.J-2a will be achieved. The City Building Official shall also be responsible for monitoring site construction to ensure that the development features proposed by the applicant to meet applicable performance standards are constructed as approved. |
Issuance of building permit(s) for residential structures intended for human occupancy within 200 feet of the Caltrain mainline track in compliance with Mitigation Measure 4.J- 2a. |