Mitigation Monitoring and Reporting Matrix (continued)

 

 

Significant Impact Being Mitigated

 

Mitigation Measure

 

Responsibility for Implementation

 

Enforcement Responsibility

Monitoring Responsibility/ Frequency

 

Actions Indicating Compliance

Traffic and Circulation (cont.)

 

phases. For the PM signal timing settings, 6 seconds of green time shall be shifted from the protected eastbound left and westbound left phases to the protected northbound left and southbound left phases.

 

 

Engineer shall inform the City Building Official, who shall not issue occupancy permits for the development until notified by the City Engineer that the requirements of Mitigation Measure 4.N-1a have been satisfied.

Because the required improvements are outside of Brisbane, permission to construct the improvements called for in Mitigation Measure 4.N-1a must be secured from the City of Daly City. The City Engineer shall work with the applicant to secure such permission.

If Daly City agrees to the improvements called for in Mitigation Measure 4.N-1a, the City Engineer shall inform the Brisbane Building Official upon completion of required improvements that occupancy permits may be issued.

If Daly City does not agree to the improvements called for in Mitigation Measure 4.N-1a, the City Engineer shall inform the Brisbane Building Official that occupancy permits may be issued upon written confirmation from Day City that such improvements will not be permitted to be constructed.

 