Significant Impact Being Mitigated |
Mitigation Measure |
Responsibility for Implementation |
Enforcement Responsibility |
Monitoring Responsibility/ Frequency |
Actions Indicating Compliance |
Traffic and Circulation (cont.) |
|||||
|
|
|
|
Building Official upon completion of required improvements that occupancy permits may be issued. If San Francisco does not agree to the improvements called for in Mitigation Measure 4.N-1d, the City Engineer shall inform the Brisbane Building Official that occupancy permits may be issued upon written confirmation from San Francisco that such improvements will not be permitted to be constructed. |
|
Increased traffic at intersections causing them to operate below acceptable levels of service Existing plus Project conditions. DSP, DSP-V, CPP, & CPP-V scenarios |
4.N-1e: The following physical improvements shall, to the extent permitted by agencies with jurisdiction over this intersection, be constructed and accepted for public maintenance prior to issuance of occupancy permits for any site-specific development that would (1) result in reducing the intersection to below the acceptable LOS standard, or (2) contribute additional traffic to the intersection if it is already operating below the acceptable LOS standard. A signal phase shall be provided for the westbound right approach at the intersection of Tunnel Avenue & Bayshore Boulevard, and signal timing settings for the AM and PM peak periods shall be modified by changing the southbound left phase from the existing permitted to protected phase, and shifting 20 seconds of green time from the northbound and southbound movements to each of the southbound left and westbound right phases |
Baylands developer |
City of Brisbane City Engineer |
The City Engineer shall maintain annual traffic counts to monitor traffic conditions, and shall provide for traffic analyses of site-specific development proposals to determine when the requirements of Mitigation Measure 4.N-1e are to be applied. If the requirements of Mitigation Measure 4.N-1e apply to a site-specific development, the City Engineer shall inform the City Building Official, who shall not issue occupancy permits for the develop- ment until notified by the City Engineer that the requirements of Mitigation Measure 4.N-1e have been satisfied. |
Installation of the physical improvements required by Mitigation Measure 4.N-1e or written confirmation from San Francisco that such improvements will not be permitted to be constructed. |