Mitigation Monitoring and Reporting Matrix (continued)

 

 

Significant Impact Being Mitigated

 

Mitigation Measure

 

Responsibility for Implementation

 

Enforcement Responsibility

Monitoring Responsibility/ Frequency

 

Actions Indicating Compliance

Traffic and Circulation (cont.)

 

As a condition of approval for the first discretionary action taken for development within the Project Site, the applicant shall be required to initiate a corridor plan for Bayshore Boulevard in cooperation with Daly City and San Francisco to determine the suite of improvements necessary to resolve long-term cumulative traffic issues along the corridor. Because the effectiveness of such a corridor plan would necessitate participation by Daly City and San Francisco in recognition of increases in traffic along the Bayshore corridor that will be generated by future development within those two jurisdictions, Brisbane will also make its best efforts to assist the developer in securing the agreement of Daly City and San Francisco to participate in the corridor study and its implementation.

 

 

Because the required improvements are outside of Brisbane, permission to construct the improvements called for in Mitigation Measure 4.N-3a must be secured from the City of Daly City. The City Engineer shall work with the applicant to secure such permission.

If Daly City agrees to the improvements called for in Mitigation Measure 4.N-3a, the City Engineer shall inform the Brisbane Building Official upon completion of required improvements that occupancy permits may be issued.

If Daly City does not agree to the improvements called for in Mitigation Measure 4.N-3a, the City Engineer shall inform the Brisbane Building Official that occupancy permits may be issued upon written confirmation from Day City that such improvements will not be permitted to be constructed.

 