Mitigation Monitoring and Reporting Matrix (continued)

 

 

Significant Impact Being Mitigated

 

Mitigation Measure

 

Responsibility for Implementation

 

Enforcement Responsibility

Monitoring Responsibility/ Frequency

 

Actions Indicating Compliance

Traffic and Circulation (cont.)

 

constructed and accepted for public maintenance prior to issuance of occupancy permits for any site-specific development that would result in reducing the interchange to below the acceptable LOS standard.

 

 

 

 

Increased traffic at

4.N-3g: Prior to issuance of occupancy permits for any

Baylands developer

City of Brisbane City

The City Engineer shall

Installation of the physical

intersections causing

site-specific development that would (1) result in

Engineer

maintain annual traffic

improvements required by

them to operate

reducing the intersection to below the acceptable LOS

counts to monitor traffic

Mitigation Measure 4.N-3g

below acceptable

standard, or (2) contribute additional traffic to the

conditions, and shall

or written confirmation from

levels of service

intersection if it is already operating below the

provide for traffic analyses

San Francisco that such

Cumulative plus

acceptable LOS standard, signal timing settings at the

of site-specific

improvements will not be

Project conditions.

Carter Street/Geneva Avenue intersection shall be

development proposals to

permitted to be constructed.

DSP, DSP-V, CPP, &

CPP-V scenarios

modified by the City and County of San Francisco to provide longer green time on eastbound/westbound permitted movements and longer cycle length.

determine when the requirements of Mitigation Measure 4.N-3g are to be

applied.

If the requirements of

Mitigation Measure 4.N-3g

apply to a site-specific

development, the City

Engineer shall inform the

City Building Official, who

shall not issue occupancy

permits for the

development until notified

by the City Engineer that

the requirements of

Mitigation Measure 4.N-3g

have been satisfied.

Because the required

improvements are outside

of Brisbane, permission to

construct the

improvements called for in

Mitigation Measure 4.N-3g

must be secured from the

City and County of San

Francisco. The City

Engineer shall work with

the applicant to secure

such permission.


Previous Page | Next Page