Mitigation Monitoring and Reporting Matrix (continued)

 

 

Significant Impact Being Mitigated

 

Mitigation Measure

 

Responsibility for Implementation

 

Enforcement Responsibility

Monitoring Responsibility/ Frequency

 

Actions Indicating Compliance

Traffic and Circulation (cont.)

 

 

 

 

the TDM program shall include:

  1. Provisions i-vi of Mitigation Measure 4.B-4;
  2. Provisions i-ii of Mitigation Measure 4.B-9;
  3. Provisions for ongoing funding of the TDM program for the life of the site-specific development project;
  4. Enforcement mechanisms, such as CC&Rs, deed restrictions, and other that will ensure ongoing implementation of approved programs;
  5. Annual reporting to the Community Development Director and the status of TDM programs and their effectiveness; and
  6. Provisions for the City to mandate TDM program modifications programs or establish additional requirements to the approved TDM (subject to C/CAG approval) should actions established in the approved TDM program prove not to be effective.

 

Previous Page | Next Page